P-Sand and cement per 100 sq ft
| Plaster | Mix | P-Sand | Cement (50 kg bags) |
|---|---|---|---|
| Ceiling, 6 mm | 1:3 | ≈ 0.09 MT | ≈ 0.5 |
| Internal wall, 12 mm | 1:5 | ≈ 0.20 MT | ≈ 0.7 |
| Internal wall, 12 mm | 1:4 | ≈ 0.19 MT | ≈ 0.85 |
| Wall, 15 mm | 1:5 | ≈ 0.25 MT | ≈ 0.9 |
| External wall, 20 mm (two coats) | 1:4 | ≈ 0.32 MT | ≈ 1.4 |
Method: area × thickness × 1.33 for dry volume, joints and wastage, split by the mix ratio; P-Sand about 1.62 t/m³ loose, cement 1,440 kg/m³. Typical estimates; uneven walls take more.
From our team
Notes, photos and examples added by the M&B Chetty team, with the author and the date.
Typical thickness and mix by surface
- Internal walls: 12 mm, 1:5 or 1:6.
- External walls: 18–20 mm in two coats, 1:4.
- Ceilings: about 6 mm, 1:3 or 1:4.
- Rough brick or uneven block walls: expect 15 mm or more in places; budget with the 15 mm row.
These are common site practice, not a standard. Your architect's or engineer's specification overrides them.
Plaster sand for a whole house
A two-storey house with 9-inch outer and 4.5-inch inner walls has roughly 4.5–5 sq ft of plastered surface per sq ft of built-up area, counting both faces of the walls and the ceilings. At 12 mm in 1:5 that is about 9 MT of P-Sand per 1,000 sq ft.
| Built-up area | Plastered surface | P-Sand | Cement for plaster |
|---|---|---|---|
| 1,000 sq ft | ≈ 4,700 sq ft | ≈ 9 MT | ≈ 33 bags |
| 1,500 sq ft | ≈ 7,000 sq ft | ≈ 14 MT | ≈ 50 bags |
| 2,000 sq ft | ≈ 9,300 sq ft | ≈ 19 MT | ≈ 66 bags |
External 20 mm plaster raises these figures; use the calculator for the outer walls separately.
Plaster calculator
| Item | Typical quantity | In loads / units |
|---|---|---|
| Results appear here (JavaScript is needed for the calculator). | ||
Typical estimate: dry mortar volume = area × thickness × 1.33, P-Sand at 1.62 t/m³, cement at 1,440 kg/m³ in 50 kg bags. Wastage on site is extra.
P-Sand price and delivery
- P-Sand ex-works: ₹680 per MT
| Area | P-Sand delivered / MT | Distance | Truck time | Quote |
|---|---|---|---|---|
| Chennai | ~₹1,313 | ~90 km | 3–3.5 h | |
| Avadi | ~₹1,239 | ~89 km | 3 h | |
| Ambattur | ~₹1,313 | ~97 km | 3–3.5 h | |
| Tiruvallur | ~₹1,134 | ~67 km | 2–2.5 h | |
| Gummidipoondi | ~₹1,134 | ~82 km | 2.5–3 h |
P-Sand comes washed from the Perindesam works in 16–20 MT tipper loads, weighed, with GST invoice and transit papers. Cement is arranged through partner suppliers.